Quant Quiz on Time & Work for Banking Exam
Attempt now to get your rank among 7969 students!
Question 1
A and B can do a work respectively in 4 days and 8 days when working alone. if they work on the alternate days then in how many days the work will be completed if A starts the work?
Question 2
One girl or two boys or three women can do a piece of work in 88 days, then one girl, one boy and one woman will do it in how many days?
Question 3
Ram can do a piece of work in 25 days which Shyam alone can finish in 20 days. Both of them worked together for 5 days and then Ram left. How many days will Shyam take to finish the remaining work?
Question 4
12 men can complete a piece of job in 56 days. In how many days can 28 men complete the same piece of job?
Question 5
Terry consumes 1600 ml of milk every day. How many litres of milk will she consume in 4 weeks?
Question 6
Six boys can complete a piece of work in 42 hours. In how many hours will 14 boys complete the same piece of work?
Question 7
3 men can complete a piece of work in 20 days. In how many days can 10 men complete the same piece-of work?
Question 8
A is 50% as efficient as B. In a given time duration C does half the work done by A and B together. If C alone does the work in 40 days, then A can do the work in?
Question 9
9 women can complete a piece of work in 19 days. How many days will 18 women take to complete the same piece of work?
Question 10
A contractor agreed to complete a work in 90 days. He engaged 48 men for the work and after doing the work for 50 days he came to know that three-fifths of the work has already been completed. How many men should he remove to finish the work in the agreed time?