ISRO Mechanical Exam: Industrial Engineering Quiz
Attempt now to get your rank among 1041 students!
Question 1
Determine critical time for the project and independent float for activity 3-4
Question 2
The demand and forecast for February are 18000 and 9725, respectively. Using single exponential smoothing method (smoothing coefficient=0.10), forecast for the month of March will be
Question 3
Consider the following activity of a network
The total float on activity 1 - 2 is
The total float on activity 1 - 2 is
Question 4
If there are m sources and n destinations in a transportation matrix, the total number of basic variables in a basic feasible solution is
Question 5
A train reservation facility has 1 counter capable of handling 100 request per hour. The person’s coming for reservation arrive at a mean rate of 90/hour. What is the average length of queue at each counter?