Basics of Project Management Short Notes Part 4

By Sachin Singh|Updated : December 20th, 2019

 Network Techniques

The predecessor to network techniques, the Gantt chart was developed, during world war I, by Henry L Gantt, for the purpose of production scheduling. An example of Gantt chart is shown below.

byjusexamprep

The Gantt chart was later modified to bar chart , which was used as an important tool in both the project and production scheduling.

byjusexamprep

The bar charts, then developed into milestone charts and next into network techniques (such as CPM and PERT).

byjusexamprep

Network Construction

A network is the graphical representation of the project activities arranged in a logical sequence and depicting all the interrelationships among them. A network consists of activities and events.

Activity

An activity is a physically identifiable part of a project, which consumes both time and resources. Activity is represented by an arrow in a network diagram. The head of an arrow represents the start of activity and the tail of arrow represents its end. Activity description and its estimated completion time are written along the arrow. An activity in the network can be represented by a number of ways: (i) by numbers of its head and tail events (i.e. 10-20 etc.), and (ii) by a letter code (i.e. A, B etc.). All those activities, which must be completed before the start of activity under consideration, are called its predecessor activities. All those activities, which have to follow the activity under consideration, are called its successor activities.

byjusexamprep

An activity, which is used to maintain the pre-defined precedence relationship only during the construction of the project network, is called a dummy activity. Dummy activity is represented by a dotted arrow and does not consume any time and resource.

byjusexamprep

An unbroken chain of activities between any two events is called a path.

Event

An event represents the accomplishment of some task. In a network diagram, beginning and ending of an activity are represented as events. Each event is represented as a node in a network diagram. An event does not consume any time or resource. Each network diagram starts with an initial event and ends at a terminal event.

byjusexamprep

Each node is represented by a circle  and numbered by using the Fulkerson's Rule. Following steps are involved in the numbering of the nodes:

  • The initial event, which has all outgoing arrows and no incoming arrow, is numbered as 1.
  • Delete all the arrows coming out from the node just numbered (i.e. 1). This step will create some more nodes (at least one) into initial events. Number these events in ascending order (i.e. 2, 3 ­etc.).
  • Continue the process until the final or terminal node which has all arrows coming in, with no arrow going out, is numbered.

An illustration of Fulkerson's Rule of numbering the events is shown in. As a recommendation it must be noted that most of the projects are liable for modifications, and hence there should be a scope of adding more events and numbering them without causing any inconsistency in the network. This is achieved by skipping the numbers (i.e. 10, 20, 30).

Rules for drawing network diagram

Rule 1: Each activity is represented by one and only one arrow in the network.

Rule 2: No two activities can be identified by the same end events.

Rule 3: Precedence relationships among all activities must always be maintained.

Rule 4: Dummy activities can be used to maintain precedence relationships only when actually required. Their use should be minimized in the network diagram.

Use of Dummy Activites

byjusexamprep

Rule 5: Looping among the activities must be avoided.

byjusexamprep

Critical Path Method(CPM)

This is based on deterministic approach in which only one time estimate is made for activity completion. The CPM (critical path method) system of networking is used, when the activity time estimates are deterministic in nature. For each activity, a single value of time, required for its execution, is estimated. Time estimates can easily be converted into cost data in this technique. CPM is an activity oriented technique.

  1. A network diagram in CPM is activity oriented.
  2. Cost is the most important criteria. Minimum is found corresponding to optimum time.
  3. There is only single time estimate for each activity.
  4. The probability of completion of activity in this estimated duration is 100%.
  5. It is based on deterministic approach.
  6. Suitable for repetitive type of work.
  7. Normal distribution is followed.

Activity times

byjusexamprep

(i) Earliest start time

 byjusexamprep

(ii) Earliest start time

EFT = EST + Activity time

byjusexamprep

(iii) Latest finish time

LFT = TL of head event

byjusexamprep

(iv) Latest finish time

LST = LFT - tij

byjusexamprep

Float

Float denotes the range within which activity time or its finish time may fluctuate without effecting the completion of the project.

(i) Total Float (FT):

FT = LST – EST or FT = LFT – EFT

byjusexamprep

(ii) Free Total (FF):

 byjusexamprepOr byjusexamprep

Where Sj = Head event slack

(iii) Independent Float (FID):

byjusexamprep

byjusexamprep

byjusexamprep

Where Si = Tail event slack

FT = 0 – for critical path FT > 0 –for subcritical path

FT < 0 – for Supercritical path

(iv) Interfering float (FIN)

It is the another name of head event slack.

byjusexamprep

CPM Systems

Mainly two systems are used in CPM analysis:

  1. A-O-A System (Activity on arrow system)

An activity is graphically represented by an arrow.

The tail end and head end of arrow represent start and finish of an activity respectively.

byjusexamprep

  1. A-O-N System (Activity on node system or precedence diagram). Activity is represented by circle or node. Events have no places. Arrows are used only to show the dependency relationship between activity nodes.

When two or more activities start parallel then an activity called DEBUT (D0) is provided at the beginning. Likewise, a finish activity (F0) is provided at the end when more than one activities finish parallel. Activity D & F have zero duration.

byjusexamprep

Programme Evaluation Review Technique(PERT)

INTRODUCTION

  • PERT was developed by the U.S Navy during the late 1950’s to accelerate the development of the Polaris Fleet Ballistic Missile PERT,
  • PERT, is abbreviated form which stands for Programme Evaluation and Review Technique used for planning,  scheduling and monitoring the project.  
  • Coordination with the help of PERT was so successful that the entire project was complete years ahead of schedule.
  • In PERT all activity time is probabilistic.
  • For PERT. Employs Beta-distribution for the time – the expectation for activity.

TIME ESTIMATES:

  • A project is composed of many diversified activities which contribute to its completion.  
  • An important characteristics of any project is its duration.  
  • As its effect and economy is often dependent on the project duration.  
  • Total project duration depends on the time taken by each activity Estimation of time required for any activity requires wide experience of similar activities.

Estimation of these time estimates can be done in two ways 

  1.  Deterministic Approach(Used in CPM): Planner has enough knowledge about the activity and gives a single estimate of the duration which is almost accurate 
  2.  Probabilistic Approach(Used in PERT): Planner does not have much idea about the activity as there is little or no past history about it. 
  • The limits with which the duration will lie,  is estimated.  
  • Pert follows the probabilistic approach and absorbs the uncertainties into the time estimates for activity and project durations.  
  • Therefore PERT is well suited for those projects where there is insufficient or no background information for estimation of time duration 
  • PERT is used in R&D type projects such as space industry,  defence industry etc.  As such projects are of non repetitive type or once-through type for which correct time estimates cannot be made.
  • Further a PERT analysis is event oriented i e in this analysis interest is more focussed on the PERT (start or completion of activity)  rather than the activities

In order to take into account, the uncertainties involved in the activity times three kinds of time estimates are made for each activity in PERT.

(i) Optimistic time (to): If everything in the project goes well.

It is the minimum time required for an activity if everything goes perfectly well without any problems or adverse conditions developed during the execution of the activity
In this time estimate, no provisions are made for delays or setbacks and better than normal conditions are assumed to prevail during the execution of the activity 


(ii) Most Likely Time (tm): It is the time for completing an activity that is best.

It is the maximum time required for an activity if everything goes wrong and abnormal situations prevail This time estimate does not include the possible effects of major catastrophes such as flood earthquakes,  fire,  labour strikes etc.


(iii) Pessimistic Time (tp): If everything in the project goes wrong.

It is the time required to complete the activity if normal conditions prevail
This time estimate lies between pessimistic and optimistic time estimates

  • In PERT activity time is probabilistic but in CPM activity time is deterministic.
  • The other difference: PERT is Event – Oriented. While the CPM is Activity – Oriented (in CPM we actually know the Activity time)

(i) Expected completion time of an Activity: (tE)

byjusexamprep

Where, t0 = Optimistic time

tp = Pessimistic time

tm = Most likely time

(ii) Standard deviation of an Activity (𝛔)

 byjusexamprep

(iii) Variance of an activity: (𝛔2)

 byjusexamprep

(iv) Central limit theorem:

(a) The mean time of the project as a whole is byjusexamprep along the critical path.

Probability of completion of project in time tE is 50%.

(b) The standard deviation of the project as a whole is byjusexamprepalong the critical path.

Critical Path: The time wise longest path is called critical path. In this path any type of delay in any event will cause delay to the project. These are shown by double line or dark lines in a network.

An event is critical if its slack is zero.

Event Time

(i) Earliest expected event occurring time (TE)

 byjusexamprep 

When there is only one path.

byjusexamprep

Where, byjusexamprep  = Expected completion time of an activity I – j

byjusexamprep …. when there are more than one path.

Where  

byjusexamprep= Earliest expected time of event i.

 byjusexamprep= Earliest expected time of event j.

(ii) Latest allowable occurrence time (TL):

 byjusexamprep

When there is only one path.

byjusexamprepWhen there are more than one path.

(iii) Slack (s): This is the time by which an event may be delayed without affecting the completion time of the project.

byjusexamprep

  • Probability Factor (z)

byjusexamprep

Where, TS = Given scheduled completion time of the project

TE = Expected completion time of the project.

σ = Standard deviation

byjusexamprepbyjusexamprep

Frequency Distribution Curve for PERT

It is assumed to be a β - distribution curve with a unimodal point occurring at tm and its end points occurring at to and tp. The most likely time need not be the midpoint of to and tp and hence the frequency distribution curve may be skewed to the left, skewed to the right or symmetric.

byjusexamprep

Key Differences Between PERT and CPM

The most important differences between PERT and CPM are provided below:

  1. PERT is a project management technique, whereby planning, scheduling, organising, coordinating and controlling of uncertain activities is done. CPM is a statistical technique of project management in which planning, scheduling, organising, coordination and control of well-defined activities takes place.
  2. PERT is a technique of planning and control of time. Unlike CPM, which is a method to control costs and time.
  3. While PERT is evolved as research and development project, CPM evolved as construction project.
  4. PERT is set according to events while CPM is aligned towards activities.
  5. A deterministic model is used in CPM. Conversely, PERT uses probabilistic model.
  6. There are three times estimates in PERT i.e. optimistic time (to), most likely time ™, pessimistic time (tp). On the other hand, there is only one estimate in CPM.
  7. PERT technique is best suited for a high precision time estimate, whereas CPM is appropriate for a reasonable time estimate.
  8. PERT deals with unpredictable activities, but CPM deals with predictable activities.
  9. PERT is used where the nature of the job is non-repetitive. In contrast to, CPM involves the job of repetitive nature.
  10. There is a demarcation between critical and non-critical activities in CPM, which is not in the case of PERT.
  11. PERT is best for research and development projects, but CPM is for non-research projects like construction projects.
  12. Crashing is a compression technique applied to CPM, to shorten the project duration, along with least additional cost. The crashing concept is not applicable to PERT.

Next - Basics of Material Science & Engineering Part 1

*****

Thanks

Prep Smart, Score Better. Go BYJU'S Exam Prep!

Comments

write a comment

Follow us for latest updates