Time Left - 12:00 mins

JE 2019 || Day 31 || Utilization of Electrical Energy Quiz 1

Attempt now to get your rank among 541 students!

Question 1

A generating station has 500 MW maximum demand and annual load factor of 50%. Capacity factor of 40%. The reserve capacity of the plant is

Question 2

The advantage of hydro-electric power station over thermal power station is

Question 3

Which of the following power stations is mainly used to cover peak load on the system?

Question 4

In what form the initial energy will be released for the 200 MeV per fission by a neutron in a slow thermal nuclear reactor?

Question 5

The high load power plant

Question 6

Which among the following information regarding HVAC Transmission System is incorrect?

Question 7

In the load-frequency control system with free governor action, the increase in load demand under steady condition is met

Question 8

The main objective of load frequency controller is to apply control of

Question 9

The incremental fuel costs for two generating units G1 and G2 are given by and where and are real powers generated by the units. The economic allocation for a total load of 250 MW, neglecting transmission loss, is given by

Question 10

A Pelton wheel turbine having a rated speed of 300 rpm is connected to an alternator to produce power at 50 Hz.
The number of poles required in the alternator is