Time Left - 15:00 mins
GATE CE 2020: Construction Management Quiz 4
Attempt now to get your rank among 1168 students!
Question 1
Which one of the following is the objective in crashing?
Question 2
When a project is crashed for a optimum duration
1) Direct cost is increased.
2) Indirect cost is increased.
3) Direct cost is decreased.
4) Indirect cost is decreased.
1) Direct cost is increased.
2) Indirect cost is increased.
3) Direct cost is decreased.
4) Indirect cost is decreased.
Question 3
The direct costs of the three activities along with their duration are given. Activities are completed in the sequence of A then B and then C. Then the minimum possible direct cost for the duration of 21 days will be
Question 4
A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?
Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 units
Activity B : 5 weeks-200 units, 4 weeks-225 units
Activity C : 3 weeks-700 units, 2 weeks-800 units
Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 units
Activity B : 5 weeks-200 units, 4 weeks-225 units
Activity C : 3 weeks-700 units, 2 weeks-800 units
Question 5
For the given project network, where numbers along various activities represent normal time.
Find the project completion expected duration (Te)?
Find the project completion expected duration (Te)?
Question 6
A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is
- 1168 attempts
- 3 upvotes
- 5 comments
Jul 19ESE & GATE CE