For the given network, after 15 days the updated status of the projects was given as:
Activities 1-2, 2-5, and 1-3 are completed.
Activity 2-4 has 5 days remaining.
Activity 5-8 has 3 days remaining.
Activity 5-6 has 2 days remaining.
Activity 3-6 has 6 days remaining.
The completion time of the project is
Activities 1-2, 2-5, and 1-3 are completed.
Activity 2-4 has 5 days remaining.
Activity 5-8 has 3 days remaining.
Activity 5-6 has 2 days remaining.
Activity 3-6 has 6 days remaining.
The completion time of the project is
Question 2
Which of the following event can have longest delay without affecting the project duration?
Question 3
A father notes that his teenage son uses the telephone. He takes no less than 5 minutes for a call and sometimes as much as an hour. 20 minutes calls are more frequent that calls of any other duration. Considered as a PERT activity a phone calls’ expected duration in minutes is
Question 4
The probability distribution taken to represent the completion of time in PERT analysis is
Question 5
In the network shown below, the number of the arrow gives the duration of the activity. The earliest expected time for event 6 to be attained is
Question 6
A, B, C, D and E are the 5 activities along the unique path of a AOA network of activities. Their characteristic are as under :
What is the possible range of project duration (in days)?
What is the possible range of project duration (in days)?