- MEASUREMENT OF MATERIAL AND WORKS
The units of measurements are mainly categorized for their nature, shape and size and for making payments to the contractor and also. The units of various items of work are specified in the following table:
S No. | Particulars of Item | Unit of measurement |
1. | Earthwork (i) Earthwork in excavation (ii) earthwork in filling in foundation trenches (iii) Earthwork in filling in plinth |
Cum Cum cum |
2. | Concrete (i) concrete in foundation (ii) Cement concrete in beam, slab (iii) Lime concrete in roof terracing (Thickness specified) (iv) Cement concrete in Lintels
|
Cum Cum Sqm
cum |
3. | Damp proof course (Thickness specified) | sqm |
4. | Brick work (i) Brickwork in foundation (ii) Brickwork in superstructure (iii) Thin partition walls (iv) reinforced brick work (v) One brick thick wall (Thickness specified) |
Cum Cum Cum Cum sqm |
5. | Stone work | cum |
6. | Wood work (i) doors and windows frames and chowkhats (ii) Shutters of doors and windows (thickness specified) (iii) doors and windows fitting (Hinges, handels etc.) |
Cum Sqm
Number |
7. | Steel work (i) Steel reinforcement bars (ii) rivet, bolt and nuts (iii) Binding of steel reinforcement (iv) Iron hold fast (v) Iron railing (vi) iron grills, iron gate and shutters |
Quintal Quintal Quintal Quintal Quintal sqm |
8. | Roofing (i) RCC slab roof (ii) LC roofs over bricks or stone slab (Thickness specified) (iii) Centering and shuttering form work (iv) AC sheet roofing |
Cum Sqm Sqm sqm |
9. | Plastering, pointing and finishing (i) Plastering, cement or lime mortar (Thickness specified) (ii) Pointing (iii) White washing, colour washing (Number of coats specified) (iv) Distempering, painting and varnishing (Number of coats specified) |
Sqm
Sqm Sqm
sqm |
10. | Flooring (i) 25 mm or 40 mm CC floor (ii) Doors and window sills (iii) 25 mm CC over 75 mm LC floor |
Sqm Sqm Sqm |
11. | Steel wooden trusses | No |
12. | Glass panels | sqm |
13. | Fixing of Glass panels | No. |
- TURNOUT OF WORK
- It is defined as capacity of doing work by a skilled labour.
- Expressed in the form of quantity of work per day
The approximate quantity of work for an average skilled labour is given in the table below:
S No. | Particulars of Item | Quantity per day |
1. | Brickwork in lime/cement mortar (i) in foundation and plinth (ii) in superstructures (iii) in arches | 1.25 cum per mason 1 cum per person 0.55 cum per person |
2. | RCC work | 3 cum per person |
3. | Plastering, pointing and finishing (i) 12 mm plaster with cement/lime mortar (ii) Pointing with cement/lime mortar (iii) Painting and varnishing doors and windows (one coat) (iv) Distempering one coat (v) 2.5 cm CC floor | 8 sqm per person 10 sqm per person 25 sqm per person 35 sqm per person 7.50 sqm per person |
4. | Cement concrete (1:2:4) | 5 cum per person |
6. | Wood work (i) sawing hard wood (ii) Sawing soft wood (iii) Timber framing sal or teak wood | 4 sqm per person 6 sqm per person 0.07 cum per person |
7. | Earthwork (i) in excavation in ordinary soil (ii) in excavation in hard soil (iii) in excavation in rock (iv) sand filling in plinth | 3 cum per person 2 cum per person 1 cum per person 4 cum per person |
- CALCULATION OF QUANTITY OF ITEM OF WORK
The analysis of rates is worked out for the unit payment of the particular item of work under two heads: Materials and Labour.
The cost of items of work = Material cost + Labour cost
Other costs included to the above cost of items of work are:
(i) Tools and Plants (T & P) = 2.5 to 3 % of the labour cost
(ii) Transportation cost (if conveyance more than 8 km)
(iii) Water charges = 1.5 to 2% 0f total cost
(iv) Overhead charges = 1.5 to 2% of total cost.
(v) Contractor’s profit = 10 %
- BAR BENDING SCHEDULE
- Bar bending schedule is a list of reinforcement bars in RCC work.
- It is presented in tabular form for easy visual reference.
The standard length of one hook is taken as 9 times the diameter of bar
Total length of straight bar hooked at both ends = L + 18D
Where, D is the diameter of bar
For 45˚ cranked or bent up bar:
The additional length of one bent up is 0.42d
Note: In the absence of detailed design, the percentage of steel in concrete may be taken as
- Lintel, slab etc. – 0.7 to 1%
- Beams – 1 to 2%
- Columns – 1 to 5%
- Foundation, raft, footing etc. – 0.5 to 0.8%
You can avail of BYJU’S Exam Prep Online classroom program for all AE & JE Exams:
BYJU’S Exam Prep Online Classroom Program for AE & JE Exams (12+ Structured LIVE Courses)
You can avail of BYJU’S Exam Prep Test series specially designed for all AE & JE Exams:
BYJU’S Exam Prep Test Series AE & JE Get Unlimited Access to all (160+ Mock Tests)
Thanks
Team BYJU’S Exam Prep
Download BYJU’S Exam Prep APP, for the best Exam Preparation, Free Mock tests, Live Classes.
Comments
write a comment