Question 1
A 5 station assembly line has allotted times 7, 9, 8, 6 and 5 minutes respectively. What is the balance delay __________?
Question 2
The annual demand for an item is 10,000 units. The unit cost is Rs. 100 and inventory carrying charges are 14.4% of the unit cost per annum. The cost of one procurement is Rs. 2000. The time between two consecutive orders to meet the above demand is _______ month(s).
Question 3
Consider the following project network, where numbers along the various, activities represent the normal time. The independent float, on activity 3-6 and the project time, respectively are _________.
Question 4
A product is assembled at 3 different at workstation. If station time is 5, 6 and 9 minutes and cycle time is 11 minutes. Find the line efficiency and the smoothness index of the assembly ___________.
Question 5
Six jobs are to be processed on a single machine. The processing time and due dates are tabulated below. Find the number of tardy jobs used EDD for the sequence that minimizes the mean tardiness is used.
Question 6
In a bottling factory, the forecast for July was 200 units with a smoothing constant of 0.3. Using 1st order exponential smoothing, what is the forecast for September________?