Time Left - 06:00 mins

AE-JE Foundation CE: Construction Management: Quiz 2

Attempt now to get your rank among 230 students!

Question 1

In construction project, the cost-slope of an activity is an indication of

Question 2

Consider the following statements regarding the slope of cost-time curve:
1) It is given by difference between normal cost and crash cost divided by crash time.
2) It is given by difference between crash cost and normal cost divided by difference between crash time and normal time.
3) It is given by difference of crash cost and normal cost divided by normal time.
4) It is given by crash cost divided by crash time.
Which of these statements is/are correct?

Question 3

Crashing of a network

1) Decreases the project completion time

2) Increases indirect cost

3) Increases number of working hours

4) May change the critical path of the network

of these, correct statement(s) is/are

Question 4

A project network diagram is shown in the figure below

Normal time and crash time for each activity are given below

The minimum time required for the completion of the project is:

Question 5

Consider following statements regarding various costs associated with a project:

(i) For any project, direct cost is increased when project duration is reduced.

(ii) Indirect cost increases with increase in project duration.

(iii) Crashing of a network decreases the direct cost.

(iv) Crashing of a network increases the indirect cost.

Correct statement (s) is/are:

Question 6

For the following detail of network, which of the following activity should be crashed first?

Question 7

Which among the following gives the least cost slope?

Question 8

In time-cost optimization, using CPM method for network analysis, crashing of activities along critical path is done starting with activity having

Question 9

Cost slope is the ratio of

Question 10

The normal duration and normal cost of activity are 27 days and Rs 55,000, respectively. The activity crash duration is 23 days, and the indirect cost is Rs 1000 per day. If the cost slope is 1700 rupees per days, then the total cost after crashing of the activity will be-
  • 230 attempts
  • 0 upvotes
  • 0 comments
Jun 6AE & JE Exams