AE-JE Foundation CE: Construction Management: Quiz 2
Attempt now to get your rank among 230 students!
Question 1
Question 2
1) It is given by difference between normal cost and crash cost divided by crash time.
2) It is given by difference between crash cost and normal cost divided by difference between crash time and normal time.
3) It is given by difference of crash cost and normal cost divided by normal time.
4) It is given by crash cost divided by crash time.
Which of these statements is/are correct?
Question 3
1) Decreases the project completion time
2) Increases indirect cost
3) Increases number of working hours
4) May change the critical path of the network
of these, correct statement(s) is/are
Question 4
A project network diagram is shown in the figure below
Normal time and crash time for each activity are given below
The minimum time required for the completion of the project is:
Question 5
(i) For any project, direct cost is increased when project duration is reduced.
(ii) Indirect cost increases with increase in project duration.
(iii) Crashing of a network decreases the direct cost.
(iv) Crashing of a network increases the indirect cost.
Correct statement (s) is/are:
Question 6
Question 7
Question 8
Question 9
Question 10